Progress Photos.

10th March 2023.

Entrance & Reception - Before.

Entrance & Reception - After.

Business Lounge - Before.

Business Lounge - After.

Level 2 West - Before.

Level 2 West - After.

Toilets - Before.

Toilets - After.

Progress Photos.

6th February 2023.

Balustrade Detailing.

Sequencing impact on Gustaf & Valchromat panels, door ingos, floor tiles and fitted furniture.

Timber balustrade capping sections must be measured & profiled onsite = timing impact.

Access platform required for high-level work = impact on lower level works.

Key = avoid damage to new ceramic floor tiles.

Gustaf Panels.

Delay on installation of panels due to balustrade detailing.

Access platform required for high-level work = impact on lower level works.

Level 0 Reception.

New ceilings and light fittings installed.

Access platform required for high-level work = impact on floor finishes.

Reception desk and fitted furniture to be lifted into place.

Level 1 Lobby.

New ceilings, light fittings, decorations and first fix joinery complete.

Carpet tiles being laid today.

Fitted furniture and Valchromat panels to be lifted into place.

Level 2 Lobby.

New ceilings, light fittings, decorations, carpet tiles and first fix joinery complete.

Fitted furniture and Valchromat panels to be lifted into place.

Progress Photos.

11th January 2023.

Level 2 West.

Level 2 Lobby.

Level 2 East.

Level 1 West.

Level 1 Lobby.

Level 1 East.

Level 0 West.

Level 0 Reception.

Level 0 East.

West & East Atriums.

Entrance Atrium.

Gustafs Panels.

Toliets.

EV Charging.

External Works.

 

Space Planning Options.

Space plan layouts and CGI videos.

 

Level 0.

Option 1 - 58 workstations = 1:22.5m2

Option 2 - 74 workstations = 1:17.7m2

Option 3 - 77 workstations = 1:17m2

Option 4 - 89 workstations = 1:14.7m2

Option 5 - 101 workstations = 1:12.9m2

Option 6 - 109 workstations = 1:12m2

Option 7 - 117 workstations = 1:11.2m2

Option 8 - 141 workstations = 1:9.2m2

Option 9 - 165 workstations = 1:7.9m2

Option 10 - 188 workstations = 1:6.9m2

Level 0 - Agile.

80 workstations & 50 agile - 130 = 1:10m2

80 workstations & 50 agile - 130 = 1:10m2

Level 0 - Sub-division.

7 suites at 119m2 = 833m2

6 suits at 101m2 = 606m2

2 suite at 95m2 = 190m2

Shared space = 870m2

Showers = 119m2

Level 1 & 2.

Option 1 - 65 workstations = 1:20.2m2

Option 2 - 77 workstations = 1:17m2

Option 3 - 77 workstations = 1:17m2

Option 4 - 93 workstations = 1:14.1m2

Option 5 - 101 workstations = 1:13m2

Option 6 - 113 workstations = 1:11.6m2

Option 7 - 121 workstations = 1:10.9m2

Option 8 - 145 workstations = 1:9.1m2

Option 9 - 165 workstations = 1:7.9m2

Option 10 - 192 workstations = 1:6.8m2

Level 1 & 2 - Agile.

98 workstations & 69 agile - 165 = 1:8m2

98 workstations & 69 agile - 165 = 1:8m2

80 workstations & 52 agile - 132 = 1:10m2

80 workstations & 52 agile - 132 = 1:10m2

Level 1 & 2 - Sub-division.

98 workstations & 69 agile - 165 = 1:8m2

3 suites at 120m2 = 360m2

3 suits at 121m2 = 363m2

1 suite at 132m2 = 132m2

1 suite at 140m2 = 140m2

Shared space = 320m2

North suite = 517m2

South suite = 784m2

High Resolution.

Example of video.

Low Resolution.

Example of video.